Facade and plastering works are performed.
Construction progress, complex updates and real estate investment news from Batumi
Facade and plastering works are performed.
In Block A, the installation of the floor slab formwork and ceramic block walling continues. In Block B, dismantling and installation of column formwork is in…
Concreting of the preparation for the 1st floor of the infrastructure building has been carried out. Block A - laying of walls with ceramic block on the 2nd…
Aqua — On the 2nd construction (1 hotel) floor measurements for installation of stained glass windows have been started. On the 19th (18th) floor the loading of…
Facade and plastering works are in progress.
On the fifth floor of Block A, the floor slab formwork is being installed. On the first floor, ceramic block walling continues. Concreting of columns in Block B…
On the second floor of block A the walls are being laid with ceramic block. The drainage system is being installed. In Block B, the installation of the floor…
Ceramic block walls are being laid on the 19th construction (18th hotel) floor. The construction of the capital fence of the hotel is in progress.
Facade and plastering works are in progress. As well as installation of vertical sewerage mains.
On the fifth floor of Block A, the floor slab formwork is being installed. On the first floor, the ceramic block walls continue to be laid. Reinforcement and…
On the second floor of block A the walls are being laid with ceramic block. The drainage system is being installed. In Block B, the installation of the floor…
Ceramic block walls are being laid on the 19th construction (18th hotel) floor. The construction of the capital fence of the hotel is in progress.
Facade and plastering works are underway, as well as the installation of vertical sewer mains.
On the fifth floor of Block A, the floor slab formwork is being installed. On the first floor, the ceramic block walls continue to be laid. Reinforcement and…
On the second floor of block A the walls are being laid with ceramic block. The drainage system is being installed. In Block B, the installation of the floor…
Ceramic block walls are being laid on the 19th construction (18th hotel) floor. The construction of the capital fence of the hotel is in progress.
Facade and plastering works are underway, as well as the installation of vertical ventilation systems.
On the fifth floor of Block A, the floor slab formwork is being installed. On the first floor, the ceramic block walls continue to be laid. Reinforcement and…
On the second floor of block A the walls are being laid with ceramic block. The drainage system is being installed. In Block B, the installation of the floor…
Ceramic block walls are being laid on the 19th construction (18th hotel) floor. The construction of the capital fence of the hotel is in progress.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st