Facade works are being carried out on the outside of the building. Inside, plastering of walls, masonry fireplaces and installation of ceramic block in…
Construction progress, complex updates and real estate investment news from Batumi
Facade works are being carried out on the outside of the building. Inside, plastering of walls, masonry fireplaces and installation of ceramic block in…
Family Club — Reinforcement of the vertical structures continues in Block A. Backfilling of the excavation slots, installation of the floor slab formwork and…
Riviera — In Block A, the building materials have been loaded onto the floors and the ceramic block walls are being laid. In Block B, reinforcement of the…
Construction materials continue to be loaded onto the floors.
Electrical and plastering works, installation of communication shafts and fireplaces continue on the floors. Facade works are underway on the exterior.
Family Club — Reinforcement of vertical structures is underway on the 5th floor of Block A. In Block B, the floor slab formwork is being assembled, the…
Riviera — Wall masonry with ceramic block is being laid in Block A. Reinforcement of the foundation slab continues in Block B. At the infrastructure building…
Construction materials are being loaded onto the floors.
Electrical and plastering work is in progress in the rooms.
Facade work is being carried out on the exterior and electrical and plastering work is being carried out in the rooms.
Reinforcement of vertical structures is being carried out in Block A. In Block B, the vertical structures formwork is being assembled, waterproofing and…
Riviera — Reinforcement of vertical structures is being carried out in Block B. In the infrastructure building, the formwork of the vertical structures is being…
Facade work is being carried out on the exterior and electrical and plastering work is being carried out in the rooms.
Concreting of the 5th floor floor slab has been completed in Block A. In Block B, the formwork of vertical structures is being assembled, waterproofing and…
Riviera — Reinforcement of vertical structures is being carried out in Block B. In the infrastructure building, the formwork of the vertical structures is being…
Facade work is being carried out on the exterior, electrical work and plastering of walls in the rooms.
In Block A, preparation for concreting of the 5th floor floor slab has been carried out. In Block B, dismantling of column formwork, installation of…
In Block A, the loading of the block to the floors has been carried out.
Loading of ceramic block onto the floors is underway.
Electrical and facade works continue, and plaster beacons are being installed.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st