Aqua — Reinforcement of the columns of the 19th construction (18th hotel) floor is in progress. Wall masonry with ceramic block is in progress on the 9th (8)…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Reinforcement of the columns of the 19th construction (18th hotel) floor is in progress. Wall masonry with ceramic block is in progress on the 9th (8)…
The walls are being laid with ceramic block on the 4 construction (3 residential) and 5 (4) floors.
Family Club — Block A: Installation of formwork for the 3rd floor floor slab is in progress. Block B: Excavation works are in progress.
In Block A, work is underway to install the formwork for the floor slab of the 3rd floor. Excavation works continue in Block B.
Aqua — Reinforcement of columns of the 19th construction (18th hotel) floor has started. Wall masonry continues on the 9th (8) floor.
Ceramic block wall masonry is in progress on the 4th construction (3 residential) and 5th (4) floors.
Aqua — Marking for vertical structures on the 18th construction (17th hotel) floor. Ceramic block wall masonry on the 8th (7) and 9th (8) floors.
Family Club — The installation of formwork for the third floor slab of the third floor of Block A is in progress.
Installation of the floor slab formwork continues on the first floor of the first half of Block A. Dismantling of column formwork in the second half of the…
Ceramic block wall masonry is in progress on the 4th construction (3 residential) and 5th (4) floors.
Family Club — Installation of the formwork for the floor slab of the first floor of Block A continues. Excavation of the excavation of Block B is underway.
Dismantling of the floor slab formwork continues on the first floor of the first half of Block A, and reinforcement of the columns is being carried out…
Aqua — Concreting of the floor slab on the 18th construction (17th hotel) floor. Ceramic block wall masonry on the 8th (7) and 9th (8) floors.
Work is underway on masonry walls with ceramic block on the 4th construction (3 residential) and 5th (4) floors.
Installation of the formwork for the floor slab of the 2nd floor of Block A is in progress. Work has begun on the excavation of Block B.
In the 1st half of Block A on the 2nd floor, dismantling of the floor slab formwork continues and reinforcement of the columns has started. In the 2nd half…
Aqua — Reinforcement of the floor slab continues on the 18th construction (17th hotel) floor. Wall masonry with ceramic block is in progress on the 8th (7) and…
Installation of the formwork for the floor slab of the 2nd floor of block A is in progress.
Block A On the 2nd half of the 2nd floor, reinforcement of columns is in progress. Block B Excavation works are in progress.
Aqua — Reinforcement of the floor slab of the 18th construction (17th hotel) floor continues. On 8 (7) and 9 (8) the walls are being laid with ceramic block.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st