1. Installation of engineering systems. — Electrical installation, 17th floor. — Installation of ventilation system, 7. 2. Installation of elevator shafts…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of engineering systems. — Electrical installation, 17th floor. — Installation of ventilation system, 7. 2. Installation of elevator shafts…
1. Arrangement of curbs for installation of stained glass structures. — Arrangement of reinforcing frame of curbs. — Arrangement of the formwork of curbs…
1. Block A. Installation of engineering systems. Installation of air-conditioning system. 2. Block A. Plasterboard framing. 3. Block A. Plastering works…
Block A 1. Plastering works. — Plastering of walls, 2, 5 floors. — Plastering of slopes, 4th floor. 2. Facade works. Facing the facade with clinker tiles. 3…
1. Installation of engineering systems. — Electrical installation, 17th floor. — Installation of ventilation system, 7. 2. Plasterboard frame installation…
1. Arrangement of reinforcement belt on the roof parapet. The work is completed on villa 1, work continues on villas 2 and 3. 2. Arrangement of curbs for…
1. Block B, C. Facade works. Plastering of the facade. 2. Block A. Facade works. Priming of facade. 3. Block B, C. Installation of double-glazed windows. Glass…
Block A 1. Plastering works. — Plastering of walls, 2, 5 floors. — Plastering of slopes, 4th floor. 2. Facade works. Facing the facade with clinker tiles. 3…
1. Installation of engineering systems. — Electrical installation, 17th floor. — Plumbing installation, 3rd floor. — Installation of ventilation system, 7th…
1. Arrangement of reinforcement belt on the roof parapet, villa 1. 2. Arrangement of curbs for installation of stained glass structures. — Arrangement of the…
Block A 1. Plastering works. — Plastering of walls, 2, 5 floors. — Plastering of slopes, 4th floor. — Plastering of the roof parapet. 2. Arrangement of gypsum…
1. Installation of engineering systems. — Electrical installation, 17–20 floor. — Plumbing installation, installation of installations, 4–5 floor…
1. Arrangement of reinforcement belt on the roof parapet, villa 1. 2. Arrangement of curbs for installation of stained glass structures. — Arrangement of the…
1. Block A, B, C, E. Facade works. Plastering of the facade. 2. Block E. Waterproofing works. Preparation of rear patios of townhouses for waterproofing works…
Block A 1. Plastering works. — Plastering of walls, 2, 5 floors. — Plastering of slopes, 4th floor. — Plastering of ventilation shafts on the roof. 2…
1. Installation of engineering systems. — Installation of electrics, 8,9 floor. — Installation of plumbing, 19th floor. — Installation of ventilation system…
1. Arrangement of reinforcement belt on the roof parapet, villa 1. 2. Arrangement of curbs for installation of stained glass structures. — Arrangement of the…
1. Block A, B, C, E. Facade works. Plastering of the facade. 2. Block E. Waterproofing works. Preparation of rear patios of townhouses for waterproofing works…
Block A 1. Plastering works. — Plastering of walls, 2, 5 floors. — Plastering of slopes, 4th floor. — Plastering of ventilation shafts on the roof. 2…
1. Installation of engineering systems. — Installation of electrics, 8th floor. — Installation of plumbing, 8th floor. 2. Installation of elevator shafts…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st