Wyndham Grand Batumi Gonio. Aqua

Real estatePublished 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electrical installation, 17–20 floor.
— Plumbing installation, installation of installations, 4–5 floor.
— Installation of ventilation system, 9–13 floor.

2. Installation of elevator shafts.
Installation of elevator equipment.

3. Arrangement of gypsum cardboard frame.
Arrangement of the framework of partitions, sewing columns, sewing ceiling.

4. finishing works, 20th floor.
Laying tiles on the balconies.

5. Work on the roof of the building.
Priming on the roof.

6. Plastering works, 9th floor.
Arrangement of decorative plaster.

7. Infrastructure building.
— Dismantling of formwork.
— Waterproofing of the basement floor.