— 1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Construction progress, complex updates and real estate investment news from Batumi
— 1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Finishing works. Plastering of inner walls, on the 1st , 4th floors. 2. Ceramic block installation. Ceramic blocks are being installed on the…
Facade works. - Plastering of facade walls, on the 2nd -20th floors. 2. Installation of drywall frames. - Installation of internal partitions, the 18th floor…
1. Wiring. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works. - Painting of the…
1. Safety bars are being installed, Villa 7 Due to weather conditions no construction work is being carried out at the site today.
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Finishing works. Plastering of inner walls, on the 1st , 4th floors. 2. Ceramic block installation. Ceramic blocks are being installed on the…
1. Facade works. - Facade works, on the 11th -20th floors. 2. Installation of drywall frames. - Installation of internal partitions, the 18th floor. 3. Mockup…
1. Plumbing and wiring. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works…
— 1. Ongoing work for formwork Installation for the of floor slab, Villa 12 The formwork installation is essential for shaping the structure, required for…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Facade works. - Facade plastering. 2. Finishing works. Plastering of inner walls, on the 4th floor. 3. Drywall frame installation, on the 4th…
1. Facade works. - Facade plastering, the 2nd – 20th floors. - Facade works, on the 11th -20th floors. 2. Installation of drywall frames. - Installation of…
1. Plumbing and wiring. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works…
1. Installation of floor slab formwork, Villa 12 The formwork installation is essential for shaping the structure, required for concrete pouring and forming its…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
— Building A 1. Facade works. - Plastering of inner walls, on the 4th floor. - Facade plastering. 2. Drywall frame installation, on the 4th floor. 3. Ceramic…
1. Facade works. - Facade works, on the 11th -20th floors. 2. Installation of drywall frames. - Installation of internal partitions, the 11th – 14th floors…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works. - Finishing of…
1. Continuation of column formwork installation, Villa 15. Column formwork is necessary for shaping and holding the desired form of concrete structures until…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st