1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling in the bathrooms, penthouses. 2. Finishing works. — Finishing…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling in the bathrooms, penthouses. 2. Finishing works. — Finishing…
1. Formwork installation for the slab, Villa 15. Setting up the formwork to shape and support the concrete pour, essential for creating the structure. 2. Start…
1. Block E. Plastering. Plastering of inner walls. 2. Block E. Insulation of the terraces. Screeding on the 3rd floor. 3. Infrastructure building. Diamond…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 3rd,7th, 12th -13th floors. 2. Installation of utilities…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling in the bathrooms, penthouses. — Grouting porcelain stoneware in…
1. Formwork installation for the slab, Villa 15. Setting up the formwork to shape and support the concrete pour, essential for creating the structure. 2. Start…
1. Block E. Plastering. Plastering of inner walls on the 1st floor. 2. Block A. Glazing and installation of stained glass windows 3. Block E. Insulation of the…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 4th,7th, 12th, 13th floors. 2. Installation of utilities…
1. Installation of ceramic granite tiles in the bathrooms, penthouses. Continued ceramic granite tiling work. 2. Finishing works. — Finishing works on the 1st…
1. Formwork installation for the slab, Villa 15. Setting up the formwork to shape and support the concrete pour, essential for creating the slab structure. 2…
1. Block E. Plastering. Plastering of inner walls on the 1st floor. 2. Block A. Glazing and installation of stained glass windows Units 3, 4 3. Block A. The…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 4th,7th, 12th floors. 2. Installation of utilities systems…
1. Installation of ceramic granite tiles in the bathrooms, penthouses. Continued ceramic granite tiling work. 2. Finishing works. — Finishing works on the 1st…
1. Formwork installation for the slab, Villa 15. Setting up the formwork to shape and support the concrete pour, essential for creating the slab structure. 2…
1. Block A. Waterproofing. Insulation installation on the terraces of the 3rd floor. 2. Block E. Installation of fire-places. Installation of flue stacks. 3…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 4th, 12th, floors. 2. Installation of utilities systems…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st