1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Construction progress, complex updates and real estate investment news from Batumi
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of ledges for the stained glass windows, the 2nd floor. The formwork installation and reinforcement of the ledges for the stained…
1. Facade works. - Facade plastering, the 2nd -20th floors. - Facade works, on the 11th -20th floors. 2. Installation of drywall frames. - Installation of…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing works. - Finishing of penthouses, on…
1. Continuation of column formwork installation, Villas 14, 15. Column formwork is necessary for shaping and holding the desired form of concrete structures…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of ledges for the stained glass, the 2nd floor. The formwork installation and reinforcement of the ledges for the stained glass…
1. Facade works. - Facade plastering, the 2nd -20th floors. - Facade works, on the 11th -20th floors. 2. Installation of drywall frames. - Installation of…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing works. - Finishing of penthouses, on…
1. Start of column formwork installation, Villas 14, 15. Column formwork is necessary for shaping and holding the desired form of concrete structures until they…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Ceramic block installation, the 3rd , 4th floors. The ceramic blocks are being installed following the technology. 2. Facade works, on the 4th…
1. Facade works. - Facade plastering. - Façade winterization, on the 7th -13th floors. 2. Installation of drywall frames. - Installation of internal partitions…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing works. - Finishing of units, on the…
1. Trench preparation for stormwater pipe risers. Ongoing works. 2. Start of column formwork installation, Villa 14 Column formwork is necessary for shaping and…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Ceramic block installation, the 3rd , 4th floors. The ceramic blocks are being installed following the technology. 2. Facade works, on the 1st…
1. Facade works, the 3rd, 4th, 7th , 8th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames…
1. Plumbing. Heating system is being tested, on the 2nd floor. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work…
1. Foundation insulation, Villa 16 Ongoing works. It is essential for improving the building's energy efficiency. 2. Trench preparation for stormwater pipe…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st