1. Installation of ceramic granite tiles in the bathrooms, penthouses. Continued ceramic granite tiling work. 2. Finishing works. — Finishing works on the 1st…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of ceramic granite tiles in the bathrooms, penthouses. Continued ceramic granite tiling work. 2. Finishing works. — Finishing works on the 1st…
1. Block A. Waterproofing. 2. Block E. Installation of fire-places. Installation of flue stacks. 3. Block E. Plastering. Facade plastering. 4. Blocks A, C, E…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 7th — 18th floors. 2. Fabrication and installation of steel arches Balconies on the 9th, 19th floors. 2…
1. Installation of ceramic granite tiles in the bathrooms, penthouses. Continued ceramic granite tiling work. 2. Finishing works. — Finishing works on the 1st…
1. Formwork removal from the floor slab, Villa 9. The formwork is removed after the concrete has cured to complete the structure and prepare for the next stage…
1. Block E. Installation of the insulation on the terraces. Winterization and screeding of the terraces. 2. Block A. Waterproofing of the terraces. 3. Block E…
Building A 1. Facade works. Plastering of facade walls, the 4th floor. 2. Installation of cast-in ledges on the balconies. The ledges are being formworked and…
1. Facade works. — Plastering of facade walls, on the 2nd -20th floors. — Facade winterization, the 4th, 12th floors. 2. Installation of utilities systems…
1. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 2. Finishing works. — Installation of moldings…
1. Formwork is being stripped off from the floor slab, Villas 9, 10. The formwork is removed after the concrete has cured to complete the structure and prepare…
1. Block E. Installation of the insulation on the terraces. 2. Block A. Waterproofing of the terraces. 3. Block E. Pouring concrete across the terraces.
Building A 1. Facade works. Plastering of facade walls, the 4th floor. 2. Installation of cast-in ledges on the balconies. The ledges are being formworked and…
1. Facade works. — Plastering of facade walls, on the 2nd -20th floors. — Facade installation, the 14th — 20th floors. 2. Installation of utilities systems…
1. Installation of ceramic granite tiles on the terraces. Continued ceramic granite tiling work. 2. Finishing works. — Installation of moldings and baseboards…
1. Infrastructure building. — Cladding of the steel columns. 2. Construction of smoke flues. Welding of flue ducts. 3. Block E. Insulation of the terraces
Building A 1. Facade works. Plastering of facade walls, the 4th floor. 2. Installation of cast-in ledges on the balconies. The ledges are being formworked and…
1. Facade works. — Plastering of facade walls, on the 2nd -20th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being…
1. Wiring and plumbing. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works…
1. Formwork is being stripped off from the columns, Villa 15. The formwork is removed after the concrete has cured to complete the structure and prepare for the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st