1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Construction progress, complex updates and real estate investment news from Batumi
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Ceramic block installation, the 1st floor. The ceramic blocks are being installed following the technology. 2. Facade works, on the 1st , 4th…
1. Facade works, the 3rd, 4th, 7th , 8th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames…
1. Plumbing. Heating system is being tested, on the 2nd floor. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work…
1. Foundation insulation, Villa 16 It is essential for improving the building's energy efficiency. 2. Trench preparation for stormwater pipe risers. Ongoing…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Ceramic block installation, the 1st floor. The ceramic blocks are being installed following the technology. 2. Facade works. Plastering of inner…
1. Facade works, the 3rd, 4th, 7th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. - Installation of…
1. Plumbing. Heating system is being tested. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing…
1. Foundation insulation, Villa 16 Essential for improving the building's energy efficiency. 2. Trench preparation for stormwater pipe risers. Due to weather…
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Ceramic block installation, the 1st floor. The ceramic blocks are being installed following the technology. 2. Facade works. Plastering of inner…
1. Facade works, the 3rd, 13th, 19th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. - Installation…
1. Plumbing. Heating system is being tested. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing…
Due to weather conditions, the construction works on the site are not being carried out today.
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of drywall profiles, on the 5th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Ceramic block…
1. Facade works, the 3rd, 13th , 19th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. - Installation…
1. Plumbing. Heating system is being tested. 2. Installation of ceramic granite tiles on the balconies Continued ceramic granite tiling work. 3. Finishing…
1. Column reinforcement, Villas 13–14 It ensures strength and stability, enhancing the building's durability. 2. Base insulation, Villas 15–16 It is essential…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st