Aqua — Balconies are framed with reinforced concrete edges, installation of plasterboard framework of internal partitions, waterproofing of engineering…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Balconies are framed with reinforced concrete edges, installation of plasterboard framework of internal partitions, waterproofing of engineering…
Reinforced column frame and column formwork, floor slab waterproofing, floor slab primer.
Facade finishing, installation of metal railings, waterproofing of fire tanks, and trial tile installation continue at the site. On the ground floor the walls…
Riviera — In block A, fireplaces are being laid. In Block B - laying of ceramic block and concreting of the parapet. In block C - installation of reinforced…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Aqua — Balconies are being framed with reinforced-concrete edges, gypsum plasterboard framework of internal partitions is being installed, and engineering…
Villas — Reinforced frame construction, reinforcement of walls and foundation bottoms, primer treatment of the floor slab and foundation abutments are in…
Finishing of the eastern and western facade, installation of metal railings, waterproofing of fire tanks, water outlets, installation of reducers is in…
Riviera — In Block A, monolithic boards for stained glass windows are being installed, drilling of technological holes in floor slabs, and installation of…
Family Club — Geodetic works are in progress at the site. Ceramic block walls continue to be laid - on the fifth floor in Block A and on the third floor in…
Aqua — Balconies are framed with reinforced concrete edges, gypsum plasterboard framework of internal partitions is installed, diamond drilling of engineering…
Villas — Dismantling of the floor slab formwork and construction of the reinforced column framework is underway.
Finishing of the northern and western facade, installation of metal railings and balusters, waterproofing of fire tanks, water outlets, and installation of…
Riviera — In Block A, monolithic boards for stained glass windows and drilling of technological holes in the floor slabs are being installed. In Block B…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B. Geodetic works are in…
Aqua — Balconies are framed with reinforced concrete edges, gypsum plasterboard framework of internal partitions is installed, diamond drilling of engineering…
Villas — Concrete preparation of the floor slab, concreting of the floor slab, lower part of the foundation, and boundary surveying are in progress at the site.
Finishing of the southern and western facade, installation of metal railings, waterproofing of the fire tank, and installation of the external sewerage system…
Riviera — In Block A, monolithic boards for stained glass windows and drilling of technological holes are being constructed. In Block B - laying of ceramic…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st