Aqua — The site continues with the framing of balconies with reinforced concrete kerbs, installation of plasterboard framework of internal partitions…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — The site continues with the framing of balconies with reinforced concrete kerbs, installation of plasterboard framework of internal partitions…
Riviera — In Block A, the installation of formwork on the terrace and fireplaces continues. In Block B, fireplaces and ceramic block are being laid, the…
Aqua — Balcony framing with reinforced concrete edges, installation of plasterboard framework of internal partitions, waterproofing of engineering holes…
The site is undergoing trenching for the external sewerage system. Electrical installation works, installation of metal fences, installation of plasterboard…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B.
Riviera — In Block A, fireplaces are being laid and formwork is being installed on the terrace. In Block B - monolith pouring of the parapet top, monolith…
Villas — Insulation of the floor slab in villas 6, 7 Reinforcement of the floor slab in villas 6 and 7. Waterproofing of the foundation wall to the floor slab…
Electrical installation works, installation of metal fences, installation of plasterboard framework of internal partitions, diamond drilling of holes continue…
Riviera — In Block A, fireplaces are being laid, the monolith of the staircases is being poured and the formwork on the terrace is being installed. In Block B…
In Blocks A and B, ceramic block masonry continues to be laid.
Aqua — Framing of balconies with reinforced concrete edges, installation of plasterboard framework of internal partitions, waterproofing of engineering holes…
Villas — Insulation of the floor slab in villas 6, 7, 8 and 9. Reinforcement of the floor slab in villas 6 and 7. Waterproofing of the foundation wall…
Facade, electrical and roofing works, installation of metal fences continue at the facility. Waterproofing of the fire tank is being carried out. A sewage…
Riviera — Fireplaces are being laid in block A. In block B - pouring of the top and monolith of the parapet, laying of ceramic block. In block E - installation…
Family Club — In Blocks A and B, ceramic block laying continues. In Block B, the concrete of the floor slab is also being poured.
Aqua — Framing of balconies with reinforced concrete edges, installation of plasterboard framework of internal partitions, waterproofing of engineering holes…
Villas — Reinforced column frame and column formwork, floor slab waterproofing, fence wall concreting are in progress.
Finishing of the eastern and western facade and digging of the sewer trench is in progress. On the ground floor - finishing of walls. On the first floor…
Riviera — Fireplaces are being laid in block A. In block B - laying of ceramic block (first floor) and concreting of the parapet. In block E - installation of…
Family Club — Ceramic block walls continue to be laid on the site - on the fifth floor in Block A and on the third floor in Block B. In Block B, concrete is…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st