Aqua — Balconies are framed with reinforced concrete edges, gypsum plasterboard framework of internal partitions is installed, diamond drilling of engineering…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Balconies are framed with reinforced concrete edges, gypsum plasterboard framework of internal partitions is installed, diamond drilling of engineering…
Floor slab formwork and adjustment of the foundation wall formwork are in progress.
Finishing of the southern and western facade, installation of metal railings, waterproofing of the fire tank, and installation of the external sewerage system…
Riviera — Plastering of arches is in progress. In Block A - monolithic boards for stained glass windows and drilling of technological holes. In Block B - laying…
Ceramic block walls continue to be laid at the site.
Aqua — Balconies are framed with reinforced concrete edges, gypsum plasterboard framework of internal partitions is installed, diamond drilling of engineering…
Villas — Reinforcement of the foundation, formwork around the perimeter of the floor slab, and formwork of the foundation wall are in progress.
Finishing of the south and west facade, connection of water supply system, installation of reducers, installation of metal railings, tying of fire pump, digging…
Riviera — In Block A, monolithic boards for stained glass windows and staircases, ventilation shafts on the roof and technological openings are being…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Reinforcement of the floor slab frame is being completed at the site.
Preparation of the lift shaft, installation of metal railings and digging of a trench for the external sewerage system are in progress. The walls are being…
Riviera — In Block A, monolithic boards for stained glass windows are being built. In Block B - laying of ceramic block (first floor) and fireplaces…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Aqua — Balconies are framed with reinforced concrete curbs, ceilings are dusted, plasterboard framework of internal partitions is installed, diamond drilling of…
Villas — Reinforcement of the fence foundation wall, formwork of the fence foundation wall, reinforcement of the floor slab, installation of formwork along the…
Finishing of the north, south and west façade continues at the site. Preparation of the lift shaft (work of a climber), connection of the water supply system…
Riviera — In Block A, monolithic boards for stained glass windows and drilling of holes in the floor slab are being installed. In Block B - laying of ceramic…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st