Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Villas — Backfilling of the base and installation of underground sewerage is in progress at the site.
On the object is the installation of guides for plasterboard on the walls of bathrooms, sewing risers aquapanels, preparation of the lift shaft (work of a…
Riviera — In Block A, monolithic boards for stained glass windows are being built. In Block B - laying of ceramic block (first floor) and fireplaces. In Block C…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Villas — Reinforced floor slab framing, floor slab insulation, fence wall reinforcement and underground sewerage are in progress.
The northern, southern and western facades are being finished, geodesic and electrical installation works are in progress. Plasterboard guides are being…
Riviera — In Block A, monolithic boards for stained glass windows are being built. In Block B - laying of ceramic block (first floor) and fireplaces. In block E…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Villas — Reinforced floor slab framing, fence foundation reinforcement and underground sewer installation are in progress.
Finishing of the northern, southern and western facades continues on site. Plasterboard rails are being installed on the walls of bathrooms, walls of technical…
Riviera — In Block B, the ceramic block (first floor), fireplaces, internal ventilation shafts and ventilation shafts on the roof, concreting of staircases is…
Family Club — Installation of safety fences is in progress at the site. In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic…
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Villas — On site insulation and reinforcement of the floor slab, dismantling of the fence, construction of a reinforced fence frame.
Finishing of the northern, southern and western facades, ventilation shafts on the roof continues at the site. The installation of plasterboard guides on the…
Riviera — In Block B, ceramic block (first floor), fireplaces, internal ventilation shafts and roof ventilation shafts are being laid. In block C - installation…
Family Club — In Block A, ceramic block walls continue to be laid (fifth floor). In Block B, ceramic block walls are being laid (on the first floor) and the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st