Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Balconies are being framed with reinforced concrete edges, ceilings are being dusted, plasterboard framework of internal partitions is being installed…
Villas — The site is undergoing backfilling of the foundation, construction of the foundation frame, waterproofing of the foundation floor slab, and concreting…
Finishing of the northern, southern and western facades, ventilation shafts on the roof, installation of metal railings continues at the site. The installation…
Riviera — In Block B, ceramic block (second floor), fireplaces and parapet are being laid, as well as laying of ventilation shafts on the roof. In block C…
Family Club — In Block A, ceramic block walls continue to be laid (on the fourth and fifth floors) and concrete spalls are removed from the staircases. In Block…
Aqua — Balconies are being framed with reinforced concrete curbs, ceilings are being dusted, gypsum cardboard framework of internal partitions is being…
The foundations are under construction at the site.
The facility is in the process of making holes in the monolithic slab for the outlet of the storm water drainage system, waterproofing of the joint between the…
Riviera — In Block B, ceramic block (second floor), fireplaces and parapet are being laid. In block C - installation of the floor slab formwork. And in Block E…
Family Club — Installation of safety fences is underway at the site. Ceramic block walls continue to be laid in Block A, on the fourth and fifth floors. Ceramic…
Aqua — Balconies are being framed with reinforced concrete curbs, ceilings are being dusted, gypsum cardboard framework of internal partitions is being…
Villas — Reinforcement and waterproofing of the floor slab and insulation of the foundation are in progress.
The installation of plasterboard rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the northern, southern…
Riviera — In Block B, ceramic block (second floor), fireplaces and parapet are being laid. In block C - installation of the floor slab formwork. And in Block E…
Family Club — Ceramic block walls continue to be laid in Block A, on the fourth and fifth floors. In Block B, ceramic block walls are being laid (on the second…
Aqua — The facility includes framing of balconies with reinforced concrete edges, waterproofing of balconies, dedusting of ceilings, installation of…
The installation of drywall rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the north, south and west…
Riviera — In Block B - ceramic block laying (second floor), laying of fireplaces and parapet, cleaning and arrangement of ceramic block (third floor)…
Family Club — Ceramic block walls continue to be laid in Block A, on the fourth and fifth floors. In Block B, ceramic block walls are being laid (on the second…
Aqua — Balconies are being framed with reinforced concrete curbs, balconies are being waterproofed, ceilings are being dusted, gypsum cardboard framework of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st