fbpx

Wyndham Grand Batumi Gonio. Aqua — 1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained glass. Preparation and installation of ledges for stained glass is ongoing. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 3. Facade work, floors 3rd, 4th , 6th , 11th. This includes the installation of facade elements on balconies. 4. Ceramic Block Installation. Installation of ceramic blocks in accordance with the technology, ensuring wall alignment and verticality. Checking all joints and angles for compliance with the design specifications. 5. Decorative casing installation. The installation of drywall frames for interior partitions, and the columns continues on the 6th -7th , 9th, 13th floors.