Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors.
— Facade plastering, the 14th — 20th floors.

2. Installation of utilities systems.
— Wiring, the 16th — 19th floors.
— Installation of water piping, the 5th — 9th floors.
— Installation of ventilation risers, the 5th — 8th floors.

3. Installation of drywall frames.
On the 11th — 16th floors.

4. Installation of suspended ceiling.
Balconies, the 4th floor.

5. Diamond drilling of the engineering openings, the roof.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

6. Elevator shaft installation.
Construction of elevator shafts with aerated blocks, on the 11th — 13th floors.

7. Infrastructure building.
Ongoing pit excavation.