Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors.
— Facade plastering, the 14th — 20th floors.

2. Installation of utilities systems.
— Wiring, the 16th — 19th floors.
— Installation of water piping, the 5th — 9th, 20th floors.
— Installation of ventilation risers, the 7th — 9th floors.

3. Fabrication and installation of steel arches.
On the balconies, the 19th floor.

4. Installation of suspended ceiling.
Balconies, the 3rd floor.

5. Diamond drilling of the engineering openings, the roof.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

6. Infrastructure building.
Ongoing pit excavation.