Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 4th, 5th, 7th, 11th
floors.
— Plastering of facade walls, the 2nd — 20th floors.

2. Installation of utilities systems.
— Wiring, the 17th floor.
— Installation of water supply manifolds, the 3rd — 9th floors.

3. Fabrication and installation of steel arches
Balconies on the 10th, 19th — 20th floors.

4. Ceramic block installation.
Construction with ceramic blocks, basement.

5. Installation of suspended ceilings.
Balconies on the 4th floor.

6. Drywall frame installation.
On the 17th, 19th -20th floors.