fbpx

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 4th, 5th, 7th,12th, 20th floors.

2. Installation of utilities systems.
— Wiring, the 17th floor.
— Installation of water risers, the 3rd — 9th floors.
— Installation of ventilation risers, the 7th — 9th floors.

3. Fabrication and installation of steel arches
Balconies on the 19th — 20th floors.

4. Drywall frame installation.
On the 17th, 19th -20th floors.

5. Floor screeding.
On the balconies, the 19th floor.

6. Insulation.
Balconies, the 20th floor.

7. Mockup installation, the 13th floor.
Furniture assembly.

8. Installation of suspended ceilings.
Balconies, the 5th floor.

9. Infrastructure building.
Ongoing pit excavation.