Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Facade winterization, the 2nd, 4th, 5th, 7th,12th, 20th floors.
— Plastering of facade walls, the 2nd — 20th floors.
2. Installation of utilities systems.
— Wiring, the 16th — 17th floors.
— Installation of hot and cold water risers, the 3rd — 9th, 11th — 17th floors.
— Installation of ventilation risers, the 7th — 9th floors.
3. Fabrication and installation of steel arches
Balconies on the 10th, 19th — 20th floors.
4. Ceramic block installation.
Construction with ceramic blocks.
5. Drywall frame installation.
On the 17th, 19th -20th floors.
6. Floor screeding.
On the balconies, the 4th floor.
7. Infrastructure building.
Ongoing pit excavation.