Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 4th, 5th, 7th,12th, 20th floors.
— Plastering of facade walls, the 2nd — 20th floors.

2. Installation of utilities systems.
— Wiring, the 16th — 17th floors.
— Installation of hot and cold water risers, the 3rd — 9th, 11th — 17th floors.
— Installation of ventilation risers, the 7th — 9th floors.

3. Fabrication and installation of steel arches
Balconies on the 10th, 19th — 20th floors.

4. Ceramic block installation.
Construction with ceramic blocks.

5. Drywall frame installation.
On the 17th, 19th -20th floors.

6. Floor screeding.
On the balconies, the 4th floor.

7. Infrastructure building.
Ongoing pit excavation.