Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Facade winterization, the 3rd, 5th, 7th, 14th floors.
— Plastering of facade walls, the 2nd- 20th floors.
2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 7th, 16th — 20th floors.
— Wiring, the 18th, 20th floor.
— Installation of the exhaust ventilation, the 11th — 12th floors.
— Installation of water connection points, the 15th -17th floors.
— Water distribution system, on the 7th, 12th, 17th, 18th, 20th floors.
3. Fabrication and installation of steel arches
Balconies on the 20th floor.
4. Suspended ceiling installation.
On the balconies, the 4th -5th floors.
5. Waterproofing
Balconies of the 11th floor.
6. Drywall frame installation.
On the 3rd- 6th floors.
7. Floor screeding.
On the balconies, the 3rd floor.
8. Delivery of materials.
Elevator equipment was delivered.
9. Stained glass window installation.
On the 3rd — 20th floors.
10. Mockup construction.
— Grinding of the ceiling.