1. Facade works.
— Facade winterization, the 4th, 7th,11th, 20th floors.
— Façade plastering, the 2nd — 20th floors.

2. Installation of utilities systems.
— Wiring, the 16th — 17th floors.
— Installation of water risers, the 3rd — 8th floors.
— Connecting manifolds to water supply risers, the 3rd — 6th floors.
— Installation of ventilation risers, the 3rd -8th floors.

3. Fabrication and installation of steel arches
Balconies on the 19th — 20th floors.

4. Drywall frame installation.
On the 17th, 19th -20th floors.

5. Floor screeding.
On the balconies, the 19th floor.

6. Insulation.
Balconies, the 20th floor.

7. Mockup installation, the 13th floor.
Furniture assembly.

8. Installation of suspended ceilings.
Balconies, the 4th floor.

9. Diamond drilling of the engineering openings, the 8th — 11th floors.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

10. Masonry works.
Installation of the ceramic blocks.

11. Infrastructure building.
Ongoing pit excavation.