Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Facade winterization, the 5th, 7th, 11th floors.
— Plastering of facade walls, the 2nd — 20th floors.
2. Installation of utilities systems.
— Installation of the exhaust ventilation, the 4th -6th floors.
3. Fabrication and installation of steel arches
Balconies on the 19th — 20th floors.
4. Suspended ceiling installation.
On the balconies, the 3rd — 4th floors.
5. Waterproofing
Balconies of the 20th floor.
6. Drywall frame installation.
On the 19th- 20th floors.
7. Floor screeding.
On the balconies, the 19th floor.
8. Installation of the elevator.
Fabrication of elevator shaft reinforcement frame.
9. Mockup construction on the 13th floors.
— Finishing works.
— Installation of railings on the central facade.
10. Diamond core drilling for engineering openings, the4th 6th, 10th -11th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.
11. Infrastructure building.
Ongoing excavating.