Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 5th, 7th, 11th floors.
— Plastering of facade walls, the 4th — 20th floors.

2. Installation of utilities systems.
— Water supply and sewage systems are being installed on the 3rd -9th, 14th- 20th floors.
— Power supply, the 8th- 9th, 18th floors.
— Installation of the exhaust ventilation, the 4th -5th floors.

3. Fabrication and installation of steel arches
Balconies on the 19th — 20th floors.

4. Suspended ceiling installation.
On the balconies, the 3rd — 4th floors.

5. Waterproofing
Balconies of the 19th — 22nd floors.

6. Drywall frame installation.
On the 19th- 20th floors.

7. Floor screeding.
On the balconies, the 3rd, 19th floors.

8. Installation of the elevator.
Installation of elevator shaft beams on the 19th — 20th floors.

9. Mockup construction on the 13th floors.
— Wallpapering.
— Installation of balcony railings on the central facade.

10. Diamond core drilling for engineering openings, the 9th -11th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

11. Infrastructure building.
Ongoing excavating.