Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 6th, 7th, 14th floors.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 3rd, 12th, 15th floors.
— Wiring on the balconies, the 20th floor.
— Installation of the exhaust ventilation, the 18th — 19th floors.

3. Diamond core drilling for engineering openings, the 7th, 9th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

4. Elevator shafts installation
Laying of gas silicate blocks, the 17th — 19th floors.

5. Fabrication and installation of steel arches
Balconies on the 19th, 20th floors.

6. Mockup construction on the 3rd, 13th floors.
— Finishing works.

7. Suspended ceiling installation.
On the balconies, the 3rd floor.

8. Waterproofing
Balconies of the 9th floor.

9. Drywall frame installation.
On the 3rd — 6th, 20th floors.