Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Plastering of facade walls, on the 2nd -20th floors.
— Facade winterization, the 4th, 12th floors.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed, the 5th, 8th, 15th floors.
— Exhaust ventilation installation, the 14th-16th floors.
— Installation of risers.
— Wiring on the balconies, the 12th — 14th, 18th — 20th floors.

3. Fabrication and installation of steel arches
Balconies on the 9th, 19th floors.

4. Stained glass window installation, the 2nd — 20th floors.
Ongoing installation of stained glass windows and glazing.

5. Mockup construction on the 13th floor.
— Finishing works.
— Facade winterization.

6. Waterproofing
On the balconies of the 16th floor.

7. Diamond core drilling for engineering openings on the 20th floor.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

8. Elevator shafts are being installed.
— Walls are being prepared in the elevator shafts.
— Laying of aerated silicate blocks, on the 3rd — 4th floors.

9. Floor screeding
The screeding is in progress on the 18th floor.

10. Drywall frame installation.
— Installation of partitions, the 19th — 20th floors.