Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Plastering of facade walls, on the 2nd — 20th floors.
— Facade winterization, the 4th,7th, 12th, 13th floors.
2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 6th — 8th, 12th floors.
— Installation of exhaust ventilation, the 17th floor.
— Wiring on the balconies, the 20th floor.
3. Fabrication and installation of steel arches
Balconies on the 9th, 19th floors.
4. Stained glass window installation, the 2nd — 20th floors.
Ongoing installation of stained glass windows and glazing.
5. Mockup construction on the 13th floor.
— Finishing works
6. Waterproofing
Balconies of the 16th floor.
7. Diamond core drilling for engineering openings, the 12th floor.
Marking and drilling of precise openings for the installation of utilities in the future hotel.
8. Drywall frame installation.
— Installation of partitions, the 15th — 18th floors.
— Construction of drywall columns, the 9th -11th floors.
9. Elevator shafts installation
— Laying of gas silicate blocks, the 5th 47th floors.