fbpx

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Plastering of facade walls, on the 2nd — 20th floors.
— Facade winterization, the 7th floor.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 5th, 13th, 18th floors.
— Installation of exhaust ventilation, the 19th floor.
— Wiring on the balconies, the 20th floor.

3. Diamond core drilling for engineering openings, the 7th -8th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

4. Elevator shafts installation
— Laying of gas silicate blocks, the 9th, 11th floors.

5. Fabrication and installation of steel arches
Balconies on the 19th floor.

6. Mockup construction on the 13th floor.
— Finishing works.

7. Floor screeding
On the balconies, the 5th — 6th floors.

8. Waterproofing
Balconies of the 7th floor.