Wyndham Grand Batumi Gonio. Aqua

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
Plastering of the facade.

2. Installation of elevator shafts.
Installation of elevator equipment.

3. finishing works, 20th floor.
Laying tiles on the balconies.

4. Plastering works, 5, 7, 18 floors.
Installation of decorative plaster.

5. Waterproofing works.
On the roof of the building.

6. Arrangement of gypsum cardboard frame.
— Arrangement of framework on balconies, 11–12 floors.
— Closing of the frame, 11–12 floors.

7. Infrastructure building.
Floor slab formwork installation, 2nd floor.