Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of elevator shafts.
— Installation of elevator equipment, preparation for installation of doors.
— Plastering in elevator shafts.

2. finishing works, 20th floor.
Laying tiles on the balconies.

3. Plastering works, 18th floor.
Decorative plastering.

4. Plasterboard frame installation works.
Arrangement of the frame on the balconies, boarding of the frame.
5. Infrastructure building.
Installation of formwork of floor slab and staircase 2 floor.