1. Installation of Engineering Systems
Electrical installation work, 13th floor.
Installation of the water supply system, 11th-20th floors.

2. Facade Works
Thermal insulation of balconies, 3rd, 5th, 12th floors.

3. Floor Screed Installation
On balconies, 8th-9th floors.

4. Arch Sheathing
On the 19th floor.

5. Infrastructure Building
Reinforcement of the floor slab.