1. Installation of engineering systems.
Electrical installation works, 13, 20th floor.

2. Facade works.
Facade insulation on balconies, 4, 6, 7, 11 floor.

3. Waterproofing works, 3rd floor.
Work on the second layer of waterproofing on balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Welding works.
Installation of posts on the roof of the building.

6. Diamond drilling of engineering holes.
For the device of communications.

7. Infrastructure building.
Installation of formwork.