fbpx

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electrical installation works, 13, 20th floor.
— Sewerage installation, sealing of systems.
— Hot and cold water supply.

2. Facade works.
Facade insulation on balconies, 4, 6, 7, 11 floors.

3. Waterproofing works, 3rd floor.
Work on the second layer of waterproofing on balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Welding works.
Installation of posts on the roof of the building.

6. Infrastructure building.
Concrete maintenance.