Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electrical installation works, 16th, 18th floor.
— Installation of ventilation system, 11–20 floors.

2. Facade works.
Facade insulation on balconies, 4, 11, 13 floors.

3. Waterproofing works, 4th floor.
Work on the second layer of waterproofing on the balconies.

4. Works in the workshop.
Fabrication of embedded parts.

5. Welding works.
Installation of posts on the roof of the building.

6. Floor screed works.
On balconies, 16th floor.

7. Arrangement of suspended ceilings.
On the 8–9 floor.

8. Installation of gypsum plasterboard frame.
Closing of the frame, 19th-20th floor.

9. Finishing works.
Tile laying on balconies, 3rd floor.

10. Closing of arches.
On the 19th floor.

11. Diamond drilling of engineering holes.
For the installation of utilities.

12. Infrastructure building.
Reinforcing the walls of the technical floor.