Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Electrical installation works, 20th floor.
2. Facade works.
Facade insulation on balconies, 4, 6, 11 floors.
3. Waterproofing works, 3rd floor.
Works on the second layer of waterproofing on balconies.
4. Works in the workshop.
Fabrication of embedded parts.
5. Welding works.
Installation of posts on the roof of the building.
6. Floor screed works.
On balconies, 17th floor.
7. Arrangement of suspended ceilings.
On the 8–9 floor.
8. Installation of gypsum plasterboard frame.
Closing the frame, 4, floor.
9. Infrastructure building.
— Reinforcement of the floor slab.
— Dismantling of formwork