Wyndham Grand Batumi Gonio. Aqua

Real estatePublished 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.

— Electrical work, 15th floor.

— Plumbing work, 20th floor.

3. Plastering work.

Installation of decorative plaster on balconies.

4. Ceiling installation work.

Installation of ceiling frames on balconies, covering of frames.

5. Drilling of engineering holes, 1st floor.

For subsequent installation of engineering systems.

6. Infrastructure building.

— Concreting of vertical structures on the 5th floor.

— Laying of ceramic blocks.