Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Electrical work: cable laying, clip installation, internet cable laying, 8th and 11th floors.
2. Installation of elevator shafts.
— Installation of elevator equipment, door installation.
— Installation of lighting in elevator shafts.
3. Plastering work.
Installation of decorative plaster.
4. Installation of plasterboard frames.
Installation of ceiling frames on balconies.
5. Infrastructure building.
Reinforcement of vertical structures on the 3rd floor.