Get a Consultation

← All news

Wyndham Grand Batumi Gonio. Aqua.

Wyndham Grand Batumi Gonio. Aqua.

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, laying electrical cables, 12th floor.

— Plumbing work.

— Installation of air conditioning pipes, 20th floor.

2. Plastering work.

Installation of decorative plaster on balconies.

3. Installation of plasterboard frame, 11th-13th floors.

Installation of frame for inter-unit partitions, covering of frame.

4. Finishing works, 19th floor.

Laying tiles on balconies.

5. Roof work.

Tie beams.

6. Infrastructure building.

Installation of floor slab formwork, 6th floor.