Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, laying electrical cables.

— Plumbing work, installation of drainage.

— Installation of air conditioning pipes.

2. Installation of plasterboard frame.

Installation of frame for inter-unit partitions, insulation of internal partitions.

3. Finishing works, 8th and 18th floors.

Laying tiles on balconies.

4. Plastering work.

— Plastering balconies.

— Plastering the facade.

5. Installation of a panoramic elevator.

Installation of formwork for balconies of panoramic elevators.

6. Infrastructure building.

— Reinforcement of vertical structures, 8th floor.

— Ceramic block masonry, 4th floor.