Wyndham Grand Batumi Gonio. Aqua.

Real estatePublished Updated 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua.

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, wiring.

— Plumbing work, 18th floor.

— Installation of air conditioning pipes, 14th-15th floors.

— Installation of ventilation system, 9th floor.

2. Plastering work.

Installation of decorative plaster on balconies.

3. Installation of plasterboard frame, 15th-16th floors.

Installation of frame for inter-unit partitions, insulation of inter-unit partitions.

4. Installation of panoramic elevator.

Installation and reinforcement of panoramic elevator slabs.

5. Installation of stained glass structures, 10th floor.

Assembly of stained glass windows.

6. Finishing work, 9th and 19th floors.

Laying tiles on balconies.

7. Infrastructure building.

-Reinforcement and installation of formwork for vertical structures, 7th floor.

— Laying ceramic blocks, 2nd floor.