Wyndham Grand Batumi Gonio. Aqua.

Real estatePublished 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua.

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, wiring.

— Plumbing work, installation of smart boxes, 18th floor.

— Installation of air conditioning pipes on floors 5–7, installation of vertical risers on floors 2–9.

2. Installation of plasterboard frame, 5th floor.

Installation of frame for inter-unit partitions, insulation of internal partitions.

3. Finishing work, 9th floor.

Laying tiles on balconies.

4. Plastering work.

Plastering balconies.

5. Roof work.

Binding posts on the roof.

6. Installation of stained glass structures, 10th floor.

Assembling stained glass windows.

7. Installation of a panoramic elevator.

Installing formwork for the balconies of panoramic elevators.

8. Infrastructure building.

— Installing formwork, reinforcing floor slabs, 7th floor.

— Laying ceramic blocks, 3rd floor.