Wyndham Grand Batumi Gonio. Aqua.

Real estatePublished 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua.

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, wiring.

— Plumbing work, installation of smart boxes.

— Installation of air conditioning pipes.

2. Installation of plasterboard frame.

Installation of inter-unit partition frames, insulation of internal partitions.

3. Finishing works, 9th and 19th floors.

Tiling of balconies.

4. Plastering works.

— Plastering of balconies.

— Plastering of the facade.

5. Roof work.

Tying up the roof trusses.

6. Installation of stained glass structures, 10th floor.

Assembly of stained glass windows, installation of side panels.

7. Installation of a panoramic elevator.

Installation of formwork for the balconies of panoramic elevators.

8. Waterproofing work.

Installation of coating waterproofing on balconies.

9. Infrastructure building.

— Reinforcement of floor slabs, 7th floor.

— Laying ceramic blocks, 3rd floor.