Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
— Electricity supply system installation, 19th floor.
— Plumbing works, 20th floor.
2. Installation of gypsum plasterboard framework.
Closing of columns, ceilings on balconies.
3. Reinforcement of beams, 2–9 floors.
4. Work on the floor screed.
On the 5th floor.
5. Plastering works.
Plastering on the balconies.
6. Arrangement of mocap, 3rd floor.
Finishing works.