Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electricity supply system installation, 19th floor.
— Plumbing works, 20th floor.

2. Installation of gypsum plasterboard framework.
Closing of columns, ceilings on balconies.

3. Reinforcing beams, 2–9 floors.

4. finishing works, 2 floor.
Laying tiles on the balconies.

5. Floor screeding works.
On the 6th floor.

6. Plastering works, 8th floor.
Plastering on the balconies.

7. Facade works.