Wyndham Grand Batumi Gonio. Aqua.
1. Installation of engineering systems.
— Installation of a fire extinguishing system.
— Plumbing work, 18th floor.
— Installation of air conditioning pipes, 17th-18th floors.
2. Plastering work.
Installation of decorative plaster on balconies.
3. Installation of plasterboard frame, 16th floor.
Installation of inter-unit partition frames, insulation of inter-unit partitions.
4. Finishing works, 19th floor.
Laying tiles on balconies.
5. Facade works.
Plastering the facade.
6. Installation of a panoramic elevator.
Installation and reinforcement of panoramic elevator slabs.
7. Infrastructure building.
— Reinforcement of floor slabs, 6th floor.
— Laying ceramic blocks, 2nd floor.