Wyndham Grand Batumi Gonio. Aqua

Real estatePublished 1 min read0 views
Share:Link copied
Wyndham Grand Batumi Gonio. Aqua

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of electrical supply system, 11th floor.
— Installation of hot and cold water supply system, 13, 15 floors.

2. Facade works.
— Facade insulation on balconies, 12–14 floors.
— Plastering of the facade, 8, 13, 19, floor.

3. Floor screeding works.
On the 13th floor.

4. finishing works, 3 floor.
Laying ceramic tiles on the balconies.

5. Works on installation of gypsum plasterboard frame.
Closing of the frame.

6. Works on the roof of the building.
Fabrication and installation of columns and posts.

7. Works on the device of elevator shafts.
Masonry works.

8. Ceiling arrangement.
On the 7–8 floor.