Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Installation of electrical system, 12th floor.
2. Facade works.
— Insulation of the facade on balconies, 11th, 13th, 16th floors.
— Plastering of the facade.
3. Works in the workshop.
Manufacturing of embedded parts.
4. Work on the floor screed.
On the 18th floor.
5. Works on the device mocap, 3rd floor.
Finishing works.
6. Plasterboard frame installation works.
Closing of walls and engineering niches.
7. Infrastructure building.
Reinforcement of vertical structures.