fbpx

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of electrical system, 12th floor.

2. Facade works.
Insulation of the facade on balconies, 12–14 floors.

3. Floor screed works.
On the 14th floor.

4. finishing works, 2, 3 floor.
Laying ceramic tiles on the balconies.

5. Mocap works, 3 floor.
Finishing works.

6. Plasterboard frame installation works.

7. Works on the roof of the building.
— Installation of columns and columns.
— Masonry works.

8. Diamond drilling of engineering holes, roofing.
For the device of communication systems.

9. Infrastructure building.
Reinforcement and concreting of the swimming pool slab.