1. Installation of engineering systems.
— Installation of electrical system, 12th floor.
— Installation of water supply system, 3, 9th floor.

2. Facade works.
Insulation of the facade on balconies, 14, 16 floor.

3. Floor screed works.
On the 14th floor.

4. Mocap works, 3rd floor.
Finishing works.

5. Finishing works, 2–3 floor.
Laying of ceramic tiles on balconies.
6. Diamond drilling of engineering holes.
For the device of communication systems.

7. Plasterboard frame installation works, 20th floor.
Closing of the frame.

8. Masonry works.
Block masonry on the roof of the building.

9. Infrastructure building.
— Reinforcement of vertical structures.
— Dismantling and installation of formwork.